Generálna oprava uhoľného kotla K5 v PGE Belchatow

GE, SA, Elektrownia Belchatow, Poland

 

Parameters: 380MWe/1100tph, 18,7MPa, 550C

 

Assembly and repair of: membrane walls, burners, pipings, Eco and Superheater bendings.

 

Materials: 13CrMo4 (1.7335), 10CrMo910 (1.7380), 15Mo3 (1.5415), 15HM, St35

Weight of installation: 2200 t. Total No. of pressure welds 66500.

 

Percentage of participation in project implementation: 50% of pressure parts

 

Manpower on site: Maximum 230, Average 180

 