Fortum Heating Plant, Rupniecibas Iela 37 Jelgava, Latvia

Parameters: 140tph

Installation of new complete biomass boiler, boiler piping, air and flue gas ducts, air and flue gas fans, HVAC, environmental systems.

Materials: X10CrMoVNb9-1, 13CrMo4, 10CrMo910, 16Mo3, P265GH, Piping from SS

Weight of installation: 1100t.

Percentage of participation in project implementation: 100% of pressure parts

Manpower on site: Maximum 120, Average 70